RV-7 N714D Construction Log

Since all aircraft builders are encouraged to keep a builder's log, and since web stuff is second nature to me, I decided early on that I would post my entire building experience here on this site, photos and all. It's not my intent to provide instruction on how to build an RV-7, but I do want to share my experience with other builders in the hope that my photos and commentary might occasionally save some poor soul a bit of aggravation by learning from my mistakes. Enjoy...

If you end up building an RV, tell Van's you found 'em here! Van's has a "finder's fee" program in effect, where you can specify another RV builder who inspired you to build. If you can honestly say this site inspired you, and I'll give you my Van's customer number for their form. Thanks!

Empennage (9/6/2001 - 10/20/2001, 200 hours)
Empennage H-Jig Completed Horizontal Stabilizer Rudder Being Skinned Completed Vertical Stabilizer and Rudder Elevators Mounted
Wings (5/1/2002 - 9/5/2002, about 400 hours)
Wing Spar w/Lots of Nutplates Wing Skeleton Coming Together Right Wing on the Stand Right Wing in the Cradle/Dolly Both Wings in the Cradle/Dolly
Ailerons (8/8/2002 - 8/21/2002, 22 hours) and Flaps (8/22/2002 - 8/30/2002, 16 hours)
Aileron Jen Riveting the Ailerons Left Aileron Flap Skeleton Flaps Completed
Fuselage (9/5/2002 - 2/16/2003, 423 hours)
Firewall A Couple of the Many Fuselage Bulkheads Dan Bucking Rivets Inside the Fuselage Aft Fuselage Drilling the Center Fuselage
Joined Center Section and Aft Fuselage Skins and Firewall in Place Brake Pedals Being Built Brake & Rudder Pedals Brake & Rudder Pedals
Fuselage Upright, Aft Deck Riveted Top Skins Drilled Seat Backs Constructed Both Wings Mated Flap Pushrod Hole Cut
Horizontal Stabilizer Attached to Fuselage Empennage Attached to Fuselage Dan Lying in Fuselage Airflow Performance Fuel Pump/Filter Front Deck Skinned
Cabin Frame Installed Custom Extended Panel and Front Deck Custom Rudder Cable Fairing Static System Custom Panel Rib Modification
Finish Kit (1/12/2003 - present, 166 hours)
Canopy on the Bed Engine Mount Installed Packed Wheel Bearings and Mounted Tires and Tubes Fitting the Canopy Frame Finished the Canopy Frame
Canopy on the Fuselage Canopy After Being Cut Finished Trimming the Forward Canopy Bubble Drilled the Rear Window Rolling on Landing Gear
Avery Jack Stand Kit
Wiring, Panel, Firewall Forward, Engine, etc. (2/28/2003 - 3/3/2004, 390 hours)
Odyssey PC680 Battery Box Cut Instrument Holes in Panel Throttle Quadrant Baggage Floor Compartment Electrical System Contactors
Almost Done With the Panel/Avionics Painted/Installed the Instrument Panel/Avionics Avionics Wired and Working Propeller Installed
Cowling, Spinner, Baffles (8/14/2003 - present, 131 hours)
Top Cowl Trimmed and Drilled to Firewall Lower Cowl Fitted Baffles Coming Together Invisible Oil Door Hinges Custom Fiberglass Filtered Airbox
Wrap-Up Work (11/15/2003 - 3/27/2004, 322 hours)
Wings on Permanently!
Phase I (3/27/2004 - 4/9/2004, 25.2 hours)
RV Grin

General Topics:

  • How Did I Get Into This? (why build your own plane?)
  • Quick Build or Slow Build? (having trouble deciding?)
  • Tip-Up vs. Sliding Canopy? (another nagging decision)
  • TOOLS (arh, arh, arh)
  • Rivets and Riveting (everything you never wanted to know about rivets)
  • How to Prime Parts (not a primer war, just my technique)
  • The Married Dude's Guide to Aircraft Building (a survival tool of sorts...)
  • Castering Wing Cradle/Dolly
  • Soundproofing the Compressor
  • Tips and Tricks
  • Insurance Coverage (cover your ass while building)
  • Loans & Financing (who can really afford all of this anyway?)
  • IFR Equipment Requirements (the rules and regs)
  • No, really. I built this stupid thing. (photos of me for the FAA)
  • Special Thanks (couldn't have done it without you)

    And now for the "good stuff"...the chronological journal of the construction of my Van's RV-7.

    Preparation

    The Decision
    How did I decide on Van's RV-7? It's kind of a long story...if you really care, I wrote up a little description of my decision-making criteria & process.

    Planning

    • July 10, 2001 - Got confirmation from FAA of my custom registration number, N747DC
    • August 10-12, 2001 -- Attended the SportAir RV Assembly workshop
    • August 27, 2001 -- Ordered the RV-7 preview plans; Ordered the Avery tool kit w/3x Gun
    • August 28, 2001 -- Faxed the order to Vans; Began converting my garage into my shop

    Shop Environment, Equipment, etc.

    Empennage

    Horizontal Stabilizer

    Vertical Stabilizer

    Rudder

    Elevators

    Finishing the Empennage

    Wings

    Waiting until I sell my Mooney to order the wings kit...
    Update 11/6/2001: I've gotten a bunch of email from lots of builders and prospective builders out there asking if I've made any progress. Nope, unfortunately I need to sell the Mooney to free up some cash to buy the next phases. One of these days I'll probably start working on the fiberglass tips on the empennage components. Be patient...I'm sure trying to be...
    Update 1/1/2002: It's the new year already, and I still haven't sold the Mooney or come up with enough cash to buy the wings. But screw it, I need to keep making progress. So I'm working on the fiberglass tips.
    Update 2/14/2002: The Mooney is SOLD!!! Time to order the wings...

    Planning, Shop Environment, etc.

    • February 15, 2002 - Faxed the wing kit order to Vans; waiting 8-12 weeks for the kit to arrive...
    • March 11, 2002 - The wings are scheduled to ship the week of April 29.
    • March 23, 2002 - THE BIG MOVE. Jen and I have moved. We rented a 26' truck but still didn't have room in there for the garage stuff (we own way too much CRAP). The new garage is full of crap, including the new landlord's desks and boxes and stuff. I'm dreading the "conversion" process. All of my shop equipment and the empennage components are still in the old garage at this point.
    • March 26, 2002 - Rented a 14' U-haul and transported the shop and the empennage to the new garage, which is still a disaster.
    • March 27, 2002 - Got confirmation from FAA of my 2nd custom registration number, N714D. I decided I wanted a shorter, easier-to-say N-number than N747DC.
    • March 30, 2002 - Having just moved, I had to start from scratch with the new garage. It was a disaster...I cleaned it up, brought in the workbenches, set up my tools, etc. Still debating about what to do with the compressor.
    • April 6, 2002 -- Shop ready for the wing jig
    • April 7, 2002 -- Put up wing jig post (woop-de-doo)

    Spars

    • May 1, 2002 -- The wing kit arrived!
    • May 2, 2002 -- Began countersinking the right spar
    • May 3, 2002 -- Finished countersinking, began riveting nutplates
    • May 4, 2002 -- Finished installing tank and inspection panel nutplates on spars; Fabricated the tiedown spacers
    • May 5, 2002 -- Finished tiedown bracket spacers; Began drilling tiedown brackets
    • May 6, 2002 -- Drilled and countersunk tiedown brackets and spacers for nutplates
    • May 7, 2002 -- Worked on rear spar components
    • May 8, 2002 -- Finished preparing spar components
    • May 9, 2002 -- Finished the tiedown and aileron bellcrank brackets; Prepped and primed the rear spars
    • May 12, 2002 -- Finished the rear spars

    Ribs

    • May 12, 2002 - Began deburring the ribs
    • May 13, 2002 -- Prepared the ribs
    • May 14, 2002 -- More rib prep
    • May 17, 2002 -- A few more days of rib prep
    • May 19, 2002 -- Finished flanging and fluting
    • May 28, 2002 - Deburred the left main rib conduit holes

    Right Wing

    Right Fuel Tank

    Left Wing

    • July 14, 2002 -- Prepped and primed ribs; Clecoed leading edge together
    • July 15, 2002 -- Riveted skeleton together; Hung wing on jig; Drilled skins
    • July 16, 2002 -- Trekked out to A/C Spruce for primer; Positioned leading edge joint plate
    • July 17, 2002 -- Drilled the leading edge and joint plate
    • July 18, 2002 -- Leading edge work
    • July 19, 2002 -- Prepped & primed leading edge ribs; Riveted leading edge top
    • July 20, 2002 -- Finished riveting leading edge
    • July 22, 2002 -- Began mounting the Gretz Aero heated pitot tube
    • July 24, 2002 -- Drilled pitot mounting bracket; Countersunk skin to spar holes
    • July 25, 2002 -- Finished countersinking spar rivet holes
    • July 27, 2002 -- Installed the leading edge landing light (minus the lens)
    • July 28, 2002 -- Finished the leading edge light; Deburred the skeleton; Installed the leading edge (skin-spar rivets); Dimpled the skeleton top side
    • August 4, 2002 -- Finished riveting the leading edge onto the spar; Deburred and dimpled wing skins
    • August 5, 2002 -- Finished dimpling top wing skins; Spot-primed countersunk flange holes; Made scarf joint
    • August 6, 2002 -- Riveted the top skins on
    • August 7, 2002 -- Squeezed remaining top skin rivets; Moved the wing into the cradle; Drilled brace and gap seal
    • August 8, 2002 -- Deburred, prepped, & primed the gap seal, flap brace, hinge brackets
    • August 9, 2002 -- Riveted the hinge brackets, gap seal, and flap brace
    • August 11, 2002 -- Deburred and dimpled bottom skins
    • August 15, 2002 -- Installed grommets and ran conduit; Ready to rivet bottom skins
    • August 25, 2002 -- Installed the pitot tube line and fittings
    • September 1, 2002 -- Began riveting the inboard bottom skin; Installed the aileron bellcrank
    • September 2, 2002 -- Tested pitot tube current draw; Finished riveting the inboard bottom skin
    • September 3, 2002 -- FINISHED SKINNING THE LEFT WING; Rigged the left aileron; Drilled the flap hinge to the wing
    • September 4, 2002 -- Finished mounting the left flap

    Left Fuel Tank

    • July 17, 2002 -- Drilled Z brackets; Clecoed tank together; Cut stiffeners
    • July 18, 2002 -- Finished Z brackets; Drilled tank to spar
    • July 19, 2002 -- Prepped & primed Z brackets; Rounded & deburred stiffeners; Initial cut attach angle
    • July 21, 2002 -- Drilled the skin to ribs and baffle; Drilled the filler ring and drain; Deburred & dimpled the stiffeners and ribs
    • July 24, 2002 -- Deburred tank skin
    • July 25, 2002 -- Dimpled the tank skin; Countersunk the filler ring; Countersunk skin-to-baffle holes
    • July 26, 2002 -- Scuffed components; Fabricated "trap door"; Cut the attach angle; Fabricated vent line retainer & anti hang-up strip; Drilled fuel level sender holes
    • July 27, 2002 -- Installed nutplates on capacitive fuel senders; Drilled BNC & vent line fitting holes
    • July 29, 2002 -- Sealed & riveted the stiffeners, filler ring, & drain flange; Finished attach angle; Fuel tank wiring
    • July 30, 2002 -- Sealed & riveted two ribs
    • August 1, 2002 -- Sealed & riveted 3 remaining interior ribs; Drilled attach angle & reinforcement plates; Trimmed capacitive plates
    • August 2, 2002 -- Sealed & riveted the end ribs & attach angle; Installed the vent line
    • August 3, 2002 -- Installed and wired the capacitor plates
    • August 4, 2002 -- COMPLETED THE LEFT FUEL TANK
    • August 5, 2002 -- Leak tested the tank, no leaks; Installed the tank on the wing

    Ailerons

    Flaps

    Fuselage

    Order, Arrival, Unpacking, Inventory
    • March 29, 2002 - Faxed in the order for the fuselage and finish kits! Woohoo!
    • April 5, 2002 - Got confirmation from Van's, estimated ship date is June 10.
    • June 11, 2002 -- Riveted & sealed the stiffeners & drain
    • June 18, 2002 -- The fuselage kit arrived!
    • September 5, 2002 -- Unpacked the fuselage components
    • September 6, 2002 -- Inventoried fuselage components
    • September 7, 2002 -- Inventoried & organized fuselage hardware

    Firewall

    Bulkheads

    Longerons & Aft Fuselage

    Center Fuselage

    Forward Fuselage

    Preparation and Riveting

    Top Skins, Cabin, Seats

    Wing Mating, Plumbing, etc.

    Mounting Tail Surfaces

    Aileron Trim, AFP Fuel Pump, Cabin Frame, Front Deck, Paint, etc., etc.

    Finish Kit

    • March 29, 2002 - Faxed in the order for the fuselage and finish kits! Woohoo!
    • April 5, 2002 - Got confirmation from Van's, estimated ship date is June 10.
    • June 18, 2002 -- The finish kit arrived!
    • December 29, 2002 -- Unpacked the finish kit

    Canopy

    Engine Mount & Landing Gear

    Other Finishing Work

    Engine, Firewall Forward, Propeller

    Systems, Electrical, Panel, Instruments, etc

    Cowling, Spinner, Baffles

    Wrap-Up

    Phase I

    Miscellaneous

    Here's my instrument panel (before the autopilot was installed; click for a larger image):
    My Instrument Panel